Building a swimming pool is one of the most exciting home upgrades you can make. But if you’re planning a custom pool, you’re probably wondering: How long does it take from design to dive?
The pool construction timeline can vary depending on pool size, shape, materials, permitting, and customization. On average, a custom pool project in Houston takes 8–12 weeks, but knowing the process ahead of time helps set realistic expectations.
At Rhino Pool Pros, we guide homeowners through every stage—from the initial design consultation to that unforgettable first swim. This guide will walk you through the step-by-step pool building process, what affects the schedule, and how to avoid delays.
For a full overview of design and planning, check out our Complete Guide to Custom Pool Construction.
Factors That Affect Your Pool Construction Timeline
Before we dive into each stage, it’s important to understand why some pools take longer than others:
Backyard size and layout – Irregular or sloped yards may require additional preparation.
Pool shape and design – A simple rectangular pool takes less time than a complex freeform or geometric design. Learn more about choosing the perfect pool shape.
Materials – Concrete pools generally take longer to build than fiberglass. (See: Fiberglass vs Concrete Pools).
Permitting requirements – In Houston, you’ll need city permits before construction begins. Learn more in our Pool Construction Permit Guide.
Custom features – Adding spas, waterfalls, outdoor kitchens, or advanced lighting will extend the schedule.
Step 1: Design & Consultation (1–2 Weeks)
The journey begins with your vision. During this stage, our designers:
Assess your yard, budget, and lifestyle needs.
Help you choose a pool shape that fits your space.
Explore features like spas, decking, and coping.
Provide a 3D design to visualize your custom pool.
This is where your dream begins to take shape. For inspiration, explore modern pool designs that combine style and function.

Step 2: Permits & Approvals (2–4 Weeks)
In Houston, city permits are required for pool construction. This step may take several weeks depending on workload and approvals. At Rhino Pool Pros, we handle the paperwork to save you time and ensure compliance.
Step 3: Excavation (1 Week)
Once permits are cleared, excavation begins. Our crew uses heavy equipment to dig out the shape of your pool. This phase is quick but requires precision to match your custom design.
Step 4: Structural Framework & Plumbing (1–2 Weeks)
Here’s where your pool starts taking real form:
Steel rebar is installed to reinforce the structure.
Plumbing lines for circulation, filtration, and water features are placed.
Electrical systems for lighting and spas are planned.
Step 5: Pool Shell Construction (2–3 Weeks)
Depending on your chosen material:
Concrete/Gunite Pools: Concrete is sprayed and cured for strength.
Fiberglass Pools: The shell is delivered and installed directly.
Learn more about choosing the right option in Fiberglass vs Concrete Pools.
Step 6: Coping, Tile, & Decking (1–2 Weeks)
This is where aesthetics shine. The pool’s tile, coping, and decking are installed to match your backyard style. See our guide on best swimming pool materials for the Texas climate.
Step 7: Equipment Installation (1 Week)
Pool pumps, heaters, and filtration systems are connected. If you’ve chosen upgrades like energy-efficient pumps or smart pool automation, this is when they’re installed.
Step 8: Plaster & Interior Finish (1 Week)
A smooth plaster or pebble finish is applied, sealing the pool interior. This not only waterproofs the pool but also defines the final look.
Step 9: Fill & Start-Up (1 Week)
Your pool is filled with water and equipment is activated. Our team balances chemicals, tests systems, and ensures everything is running smoothly.
Step 10: Landscaping & Outdoor Features (Optional, 1–3 Weeks)
To complete your backyard oasis, you may choose extras like:
Outdoor kitchens
Fire pits and seating areas
Custom lighting
Spas or waterfalls (see: Adding Spas to Custom Pools)
Rhino Pool Pro's
Start Your Pool Journey Today
Ready to make a splash? Contact us for a free consultation and see how Rhino Pool Pro’s can transform your outdoor space into something extraordinary.
Step 11: First Swim & Handover
The most rewarding stage—the first dive into your brand-new pool! We provide guidance on pool care and maintenance so you can enjoy worry-free ownership.
For long-term tips, see our guide on pool maintenance essentials.
Average Pool Construction Timeline at a Glance
Stage | Timeframe |
---|---|
Design & Consultation | 1–2 Weeks |
Permits & Approvals | 2–4 Weeks |
Excavation | 1 Week |
Framework & Plumbing | 1–2 Weeks |
Pool Shell | 2–3 Weeks |
Tile, Coping & Decking | 1–2 Weeks |
Equipment Installation | 1 Week |
Plaster & Finish | 1 Week |
Fill & Start-Up | 1 Week |
Landscaping & Extras | 1–3 Weeks |
Total Estimated Time | 8–12 Weeks |
Why Rhino Pool Pros is the Right Choice
The pool construction timeline can seem overwhelming, but with the right team, it becomes an exciting journey. Rhino Pool Pros brings years of expertise in custom pool construction across Houston, handling design, permits, and build with precision.
✅ Local expertise in Houston permitting
✅ Custom designs tailored to your backyard
✅ Durable materials built for Texas climate
✅ End-to-end project management
👉 Ready to start your dream pool? Contact Rhino Pool Pros today for a free consultation and personalized design plan.
FAQs About Pool Construction Timeline
Most custom pools in Houston take 8–12 weeks, depending on design complexity and permits.
Yes. Heavy rain or extreme heat can delay excavation, curing, or plastering stages.
Absolutely. Permits in Houston can add 2–4 weeks before construction begins.
Fiberglass pools generally install faster than concrete or gunite pools.
Yes. Features like spas, fire pits, or kitchens can be added after your pool is built, though it’s easier to plan them in advance.